Dear Experts,
I have run the standard cost estimate on 1st Nov 2015 but one of my material price is highly fluctuating so i have to run the cost estimate again in the same period 30 Nov 2015 itself. So the existing cost estimate has been released in 1st Nov 2015, If i want run the cost estimate again in the same period means as per SAP standard functionality the system won't allow to run the cost estimate in this case. Do i need to delete the cost estimate by using the (T.Code CKR1) with subject to what are the prerequisites need to take care (If the Material Ledger is not activated).
what i suppose to do? Can you please some body suggest me ?
Thanks in advance,
Venkat