SAP is inputting a cost center when the WBS entered into the system. This is happening for only one particular WBS
I just enter WBS and SAP addes cost centre 399000 automatically
![1.png]()
whn i check in PRPS table the responsible CC is different ( 393000 is assigned to WBS)
![2.png]()